What Steps, Licenses, and Permits Does Denison Mines Need Before First Uranium Production?
August 5, 2025
Uranium mining Denison Mines
To achieve first production by mid-2028 on Wheeler River Project, Denison Mines Corp. must navigate a complex regulatory framework involving federal and provincial approvals, secure operational permits, and address social and financial obligations. Below is a comprehensive outline of the required steps, licenses, and permits, their current status, and their importance, with additional details on regulatory intricacies and potential risks. This article is just my opinion, it is not paid or sponsored, but I do own shares of Denison Mines!
1. Environmental Assessment (EA) Approvals

  • Federal Environmental Assessment (Canadian Nuclear Safety Commission - CNSC):
    • Denison must complete an Environmental Assessment under the Canadian Environmental Assessment Act, 2012 (CEAA 2012) to demonstrate that the Wheeler River Project will not cause significant adverse environmental effects, particularly to groundwater, wildlife (e.g., bat habitats), and local ecosystems.
    • Key Milestones:
      • Submitted a Project Description in May 2019, initiating the federal EA process.
      • Delivered a Draft Environmental Impact Statement (EIS) in October 2022, followed by responses to 238 Information Requests from the Federal Indigenous Review Team (FIRT) in July and August 2023.
      • Completed the technical review by November 2024 and submitted the Final EIS on November 22, 2024, which is currently under a 30-day CNSC review to confirm compliance with regulatory requirements.
      • Public hearings are scheduled for October 8 and December 8–12, 2025, where Denison will address concerns from regulators, Indigenous groups, and the public. These hearings will inform the CNSC’s EA report and licensing decision.
    • Significance: The federal EA is a prerequisite for any CNSC licensing. It requires Denison to prove that ISR operations—using a lixiviant to dissolve uranium underground—won’t contaminate groundwater or harm biodiversity. Public and Indigenous input during hearings could raise issues, potentially requiring additional mitigation measures.
    • Potential Challenges: Delays could arise if new environmental concerns (e.g., groundwater modeling deficiencies) emerge during hearings, or if public opposition intensifies. ISR is relatively untested in Canada, so regulators may impose stricter scrutiny.
    • Status: Nearing completion. The Final EIS is under review, with a decision expected post-hearings in late 2025 or early 2026.

 

  • Provincial Environmental Assessment (Saskatchewan Ministry of Environment):
    • The project is subject to Saskatchewan’s Environmental Assessment Act, requiring a separate provincial review to ensure compliance with environmental standards.
    • Denison submitted a Technical Proposal in 2019, aligning the provincial EA with the federal process to streamline efforts.
    • On August 5, 2025, the Saskatchewan Ministry of Environment granted Ministerial Approval, confirming that Denison’s environmental management plans meet provincial requirements.
    • Significance: This approval is a major milestone, validating Denison’s ISR technology and mitigation strategies for waste, water, and emissions. It allows the project to proceed to provincial permitting.
    • Potential Challenges: None remain, as provincial approval has been secured.
    • Status: Complete.

2. CNSC Licensing (Federal)

  • License to Prepare Site and Construct:
    • Under subsection 24(2) of the Nuclear Safety and Control Act (NSCA), Denison requires a CNSC license to prepare the site (e.g., build roads and infrastructure) and construct the ISR mine and processing facility. The application was submitted in July 2023, per the Uranium Mines and Mills Regulations.
    • The CNSC will finalize its decision after the December 2025 public hearings, contingent on federal EA approval. The license will cover site preparation and construction activities, ensuring compliance with safety and radiation protection standards.
    • Significance: This license is critical to begin physical work on the project. It ensures that construction adheres to nuclear safety protocols and environmental commitments outlined in the EA.
    • Potential Challenges: Delays in the EA process or unresolved concerns from hearings could push back the licensing decision. The CNSC may also require additional safety measures due to the novelty of ISR in Canada.
    • Status: Under review, with a decision expected in late 2025 or early 2026.
  • Operating License:
    • Before production can begin, Denison must obtain a CNSC operating license to run the mine and process uranium. This license will be applied for after construction (likely 2027–2028) and will require proof that the completed facility meets safety, environmental, and operational standards.
    • The license will cover ISR operations, including lixiviant injection, uranium extraction, and yellowcake production, as well as radiation monitoring and waste management.
    • Significance: This is the final regulatory hurdle before production. The CNSC will verify compliance with Canada’s nuclear safety framework and international non-proliferation obligations.
    • Potential Challenges: Any construction issues or operational plan deficiencies could delay approval. The CNSC’s rigorous oversight ensures no shortcuts are taken.
    • Status: Not yet applied for; will follow construction completion.

3. Provincial Permits (Saskatchewan)

  • Pollutant Control Permits:
    • The Saskatchewan Ministry of Environment requires permits to manage emissions, effluents, and waste under the Environmental Management and Protection Act. For ISR, this includes handling the lixiviant, treating wastewater to prevent groundwater contamination, and storing waste rock or tailings.
    • These permits ensure compliance with provincial air and water quality standards, critical for a project involving underground fluid injection.
    • Significance: These permits are essential to operate legally and avoid environmental violations. They address public and regulatory concerns about ISR’s potential impacts on water resources.
    • Potential Challenges: Securing these permits requires detailed technical submissions, and any gaps in Denison’s waste or water management plans could cause delays.
    • Status: Not explicitly detailed in recent updates, but typically secured closer to construction or operation (2026–2027). Likely in progress.
  • Surface Lease Agreement:
    • Denison must secure a surface lease agreement with the Province of Saskatchewan to legally access and use the Wheeler River site for mining activities, including facilities, roads, and power infrastructure.
    • This is a standard requirement for mining projects in Saskatchewan, formalizing land use rights.
    • Significance: Without this lease, Denison cannot legally build or operate on the site. It ensures clarity on land rights and responsibilities.
    • Potential Challenges: This is typically straightforward but requires coordination with provincial authorities and may involve negotiations on terms.
    • Status: Not mentioned in recent updates, but likely in progress or to be finalized before construction (2025–2026).
  • Additional Provincial Permits:
    • Other permits may be required for specific activities, such as water extraction for ISR operations, waste storage, or infrastructure development (e.g., connecting to Saskatchewan’s power grid).
    • These are governed by provincial regulations and tailored to the project’s scope.
    • Significance: These permits ensure all ancillary activities comply with provincial laws, preventing operational delays.
    • Potential Challenges: The number and complexity of permits depend on project specifics, and unanticipated requirements could arise during construction.
    • Status: Not specified, but will be addressed before or during construction.

4. Indigenous and Community Agreements

  • Denison has engaged with Indigenous communities, including the English River First Nation, Kineepik Métis Local #9, and the Village of Pinehouse Lake, signing agreements like the Shared Prosperity Agreement. These outline economic benefits (e.g., jobs, training) and address impacts on Indigenous rights.
  • While not formal permits, these agreements are critical for regulatory approval, as the EA process requires evidence of meaningful consultation and accommodation. They also support Denison’s social license to operate.
  • Significance: Strong community support minimizes legal or public relations risks. Unresolved Indigenous concerns could lead to challenges during public hearings or even legal action, as seen in other Canadian resource projects.
  • Potential Challenges: Ongoing engagement is needed to address any new issues raised during the 2025 hearings. Failure to maintain trust could complicate approvals.
  • Status: Multiple agreements are in place, with continued consultation to ensure community support through the regulatory process.

5. Additional Requirements

  • Financial Guarantee:
    • The CNSC requires a financial guarantee to cover decommissioning costs, ensuring funds are available for site cleanup and environmental restoration after the mine closes. This is calculated based on the project’s environmental risks and closure plan.
    • Significance: This is a mandatory condition for the operating license, protecting taxpayers from future liabilities. It’s a significant financial commitment for Denison.
    • Potential Challenges: Securing the guarantee requires substantial capital or bonding, which could strain Denison’s finances if market conditions are unfavorable.
    • Status: Not detailed in recent updates, but must be in place before the operating license is granted (2027–2028).
  • Detailed Engineering and Financing:
    • While not regulatory requirements, completing detailed engineering designs and securing project financing are critical prerequisites. Denison contracted Wood in February 2024 for engineering, focusing on ISR well fields, processing plants, and infrastructure.
    • The Feasibility Study (August 2023) estimates capital costs at ~$419 million CAD. Denison must secure funding through equity, debt, or partnerships to cover construction.
    • Significance: Engineering ensures the project meets regulatory and operational standards, while financing is essential to start construction. Delays in either could push back the timeline.
    • Potential Challenges: Uranium price volatility or investor hesitancy could complicate financing. Engineering delays or design revisions could also impact the 2026 construction start.
    • Status: Engineering is ongoing; financing details are not publicly disclosed but must be finalized before construction.

Timeline to First Production

  • Current Status (August 2025):
    • Provincial EA approval secured (August 5, 2025).
    • Federal EA nearing completion, with the Final EIS under review and public hearings scheduled for October and December 2025.
    • CNSC license to prepare site and construct is under review, pending EA approval.
  • Next Steps:
    • Complete federal EA and secure CNSC construction license by early 2026.
    • Obtain provincial pollutant control permits and surface lease agreement (2025–2026).
    • Begin construction in early 2026, expected to take 2–3 years.
    • Apply for and secure CNSC operating license post-construction (2027–2028).
    • Achieve first production by mid-2028, per Denison’s timeline.
  • Potential Risks:
    • Public hearings may uncover new environmental or community concerns, delaying EA or licensing decisions.
    • Financing challenges could arise if uranium markets weaken or investor confidence wanes.
    • ISR’s novelty in Canada may prompt additional regulatory requirements, extending timelines.
    • Construction delays or cost overruns could push back the production target.

Denison Mines Corp. has secured provincial EA approval and is close to completing the federal EA, with CNSC public hearings in late 2025 as the next milestone. Remaining requirements include the CNSC license to prepare site and construct (expected early 2026), provincial pollutant control permits, a surface lease agreement, and a future operating license (2027–2028). Indigenous agreements, a financial guarantee, and finalized engineering and financing are also critical. If approvals and financing align, construction will begin in early 2026, leading to first production by mid-2028. For the latest details, visit denisonmines.com.

Join our Newsletter!

Sign up to our free monthly newsletter to recieve the latest on our interviews and articles.

By subscribing you agree to receive our newest articles and interviews and agree with our Privacy Policy.
You may unsubscribe at any time.